Supplied Photo
The City of Lloydminster will begin Phase 1 of its Central Business District Replacement Program this spring, marking the beginning of a 15-year transformation of the city’s downtown core into a welcoming and thriving area.
The Downtown Area Redevelopment Plan (DARP) will catalyze the redevelopment of downtown Lloydminster into a vibrant community and the social and economic heart of the city where businesses thrive and people want to live, play and visit.
“This is a significant milestone for the City of Lloydminster,” said Mayor Gerald Aalbers. “We believe revitalizing our downtown core will positively impact our community, and we’re excited to see the transformation begin.”
Adopted by City Council in 2020, and after extensive planning and consultation, the initial roadway construction is expected to begin mid-to-late-May.
The long-term revitalization project aims to create a downtown core that will attract residents and visitors alike. Phase 1 of the Central Business District Replacement Program will focus on replacing the underground infrastructure within 50 Street, between 49 Ave. and 50 Ave., including both intersections and aboveground improvements, which include adapting the existing roadway cross-section, installing new sidewalks, street lighting, street furniture, traffic lights and landscaping.
In addition to the physical improvements, such as an upcoming façade grant, the City’s Economic Development department is committed to supporting local businesses during construction. Measures will be implemented to ensure businesses remain accessible and minimize disruption to their operations.
“We understand the vital role that businesses play in our city’s economic growth and are dedicated to providing the resources and tools they need to succeed. As we embark on the downtown revitalization project, we’ll work closely with local businesses to ensure that the process is as smooth as possible and that their needs are considered,” said Katlin Ducherer, Economic Development Officer.
The City of Lloydminster is also committed to engaging with residents throughout the project and welcomes feedback and input on these revitalization efforts. Information on the project, including updates and timelines, will be posted at Lloydminster.ca/CBDRP and on social media channels.
The City of Lloydminster would like to thank all residents, businesses, and community partners for their patience and support as we embark on this exciting journey to revitalize our downtown core.
About the Central Business District Replacement Program
The program consists of replacing and upgrading underground municipal infrastructure throughout the downtown core to maintain the serviceability and longevity of our systems. Further work includes removing and reconstructing the surface works cross-section (i.e., roadway surface, sidewalks, and other public amenities) to bring the DARP’s vision to life.
Visit Lloydminster.ca/CBDRP to learn more about the central business district replacement program. This web page includes the project’s scope, traffic accommodations (once approved) and will host regular project updates.
Project Funding
The Central Business District Replacement Program – Phase 1 is funded through the general government capital reserve, the environmental services capital reserve, the business improvement district restricted reserve and the Canada Community Building Fund. The Central Business District Replacement Program – Phase 1 project has an approved capital budget of $5,310,000. The anticipated costs associated with the project are:
FUNDING SOURCES | ||
General government capital reserve
Environmental services capital reserve Canada Community-Building Fund Business improvement district restricted reserve |
$891,000.00
$2,292,804.00 $1,441,196.00 685,000.00 |
$5,310,000.00 |
CONSTRUCTION CONTRACTOR | ||
Consultant costs
Geotechnical materials testing allowance
Construction costs Construction tender amount Construction contingency (5%)
Utility rehabilitation Traffic light design-build contractor Streetlight replacement by ATCO Electric Ltd. |
$100,000.00
$4,410.419.16 $220,520.95
$260,707.45 $317,578.40 |
$100,000.00
$4,630,940.11
$578,285.85 |
Remaining Budget
$774.04 |